Hello Team,
I have Quick question to ask.
I am bit confused with graph in Sprint report
image2015-8-4 12:58:21.png
Can any one of you please explain the above graph,
1)what does Red line,Green line and Grey Line Indicate here.
2)why is the Red line started from the top? and why is it decreasing ?
3)what does Grey line indicate,why is it started from Top and Gradually decreased
Thanks,
Yogashree.M
Guide line means the optimal way the sprint progresses. The Estimate decreases consistently, stabilizes at few instances and then reach zero at the end of the sprint (last day of sprint)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Redline - remaining values.
Grey - provides guideline for the progress
Greenline - progress of the sprint
It provides the correct data after the sprint completion
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Red line explains how the Story points are actually burnt (in your case team hours)
Grey line is is ideal line for comparison with the Red line.
I dont see a Red line. Which version of JIRA Agile are you using
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.