http://blogs.atlassian.com/2013/04/how-to-manage-a-product-backlog-with-ease/
It is suggested to use a Kanban board as a PM board, with swimlanes by epics. But where and how do you assign issues to Epics given that the epic panel is not visible on Kanban boards. Do you edit each issue and use the Epic link drop down are is there a more drag-n-drop way?
You'll need to add the Epic Link by editing Issues, there's no way to manage Epics in Kanban Boards similar to Scrum Boards' Plan mode.
That's what I was afraid of, but good to know for sure, thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is a feature request but unfortunately Atlassian doesn't seem to care about it very much. https://jira.atlassian.com/browse/GHS-7052
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sadness...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Why is the Kanban board always crippled? It used to not have the backlog, now it does. but no epics. which is why i've always used a neverending sprint on the scrum board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.