Hi,
I wonder how can bulk postpone some related issue start duedate. For example, if A blocks B issue, B block C issue, if A need to postpone 2 days, how can I bulk change B & C issue start date and end date? see attached plan image:
I have found below answers, but not suit for me yet.
1. I can not find "Change Task mode", and I have not installed Gantt either——Refer to [Big Picture] Bulk Change Scheduling Mode (atlassian.com)
2. Refer to How Can I set the due date of Subtask A to be the ... (atlassian.com)
It told me to customize various filters and automation, which seems not very convenient?
Thanks
WeiLin
Hello @Wei Lin
I see that you referenced a post where I supplied the answer.
There are only two options for automating the task. One option is the automation rule solution I provided in the other post.
The other option is to use the Automated Schedule feature of Jira Plans, available in the Premium edition. I don't think that option actually will meet your requirement, but you can learn more about it here:
Jira does not otherwise natively provide a feature to update dates for a sequence of linked issues.