Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to calculate date difference between planned due date and date when status was changed to accept

Devashish Kedar November 19, 2024

 

 

the date difference between a planned due date and the date when the status of an issue was changed to “Accepted,”

There are no particular to capture actual end date . Should i create a custom variable ? 

2 answers

2 accepted

0 votes
Answer accepted
Tomislav Tobijas
Community Champion
November 19, 2024

Hi @Devashish Kedar ,

This is usually achieved by using Jira automation as there is no native functionality to track baselines and actual start/end dates. If you're already using the system due date field as the date for when the completion is planned, you could create an additional date field (such as 'End date') to capture this information.

So, once you've got this second date field, you can create automation which would trigger once issue is transitioned to status "Accepted" and then just update the value of the date field (maybe by using smart values such as {{now}} or something similar; depending on the use case).

Hope this helps.

Cheers,
Tom

0 votes
Answer accepted
Rudy Holtkamp
Community Champion
November 19, 2024

Hi @Devashish Kedar ,

You can create a new date field, with accepted date, and fill that when the issue transitions to accepted with e.g. Jira automation or a post function

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events