Hello

Currently my story workflow is as follow: 

To Do => In progress => Done

I want to add another end status which is "Cancelled", so i can move the story from To Do or In progress to Either "Done" or "Cancelled". I want to have the following option in my Workflow:

To Do => In progress => Done

To Do => Cancelled 

When i tried to add cancel status, it is added as middle status, even when i moved it through the board , i couldn't manage to branch (split) the end status to either Done Or Cancelled 

 

Thanks for your help in advance. 

2 answers

2 accepted

1 vote
Answer accepted
Géraud Benazet
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 20, 2021

I like the first solution better. Here's a walkthrough for the newbies like me :

  • Open your workflow : Issues > Workflows > Choose your workflow and click Edit
  • Add a new status and check the box "Allow all statuses to transition to this one"
  • In text view, edit the transition to the new status, for exemple Cancelled (51) >> Cancelled
  • Add a post function to change the resolution. Post Function > Add post function > Update issue field > Add > and change issue field to "Resolution" and Field value to "Won't do".
Derek Wright
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 30, 2021

Thank you!

rskira July 2, 2021

Wery nice answer it helps me. And I spend some time t find it. Maybe my flow helps someone too.

  • project settings
  • workflows-> (edit pen sign)
  • Diagram -> add status -> move it on diagram under in progress
  • Click on Text near Diagram -> Click on Cancelled -> the same -> post function
    post function could be not editable look above you should see notification "You are editing a draft workflow"
0 votes
Answer accepted
Jack Brickey
Community Champion
October 29, 2019

There are two ways to do this:

  1. Create a new Cancelled status w/ a Done Category and set up the transitions as desired. Likely just use "All".
  2. Create a Cancelled Resolution and continue to use Done but set the Resolution to Cancelled when you cancel a request.

Generally I like #2

If you need detailed assistance LMK.

Jessica Karen Vazquez Neve Villasenor
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 10, 2021

Hi, 

Thanks for the response, it is very helpful, however I have a problem: I would like to apply the first way, but my JIRA instance has the message like <<You can only have one "Done" status.>> Do you know why?

 

image.png

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events