Hello everyone !

- I have a task A in a project 1

- I have tasks B, C and D in a project 2

Tasks B, C and D are blocked by Task A

Is it possible to change status of Task A when Status of Tasks B, C and D changes ?

Thanks for your help :) 

1 answer

0 votes
John Funk
Community Champion
December 5, 2019

Hi @ryzwan - Welcome to the Atlassian Community!

This is not possible out of the box with Jira, but you should be able to do it with an add-on like Automation for Jira or ScriptRunner. 