I have created Scrum Project. I have create two week sprint for task for development. After developer finished that task, I want to assign that task to tester and change the type to Ready for Testing. So Tester prepare their sprint. May I know how to achieved.
I have created "Ready for Testing" Sub Task but I can see it.
Regards,
Alex
Sub-tasks are not sprint items, they are parts of their parent issues, so you can't do this.
You need to either include testing as part of the sprint (which is the way you should be working if you're doing Scrum-like stuff like sprints), or create separate linked items for your test team.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.