Sridhar Gandla July 20, 2018

I want to clear Due date for 100+ Issues using bulk change. When I give NULL, EMPTY or SPACES it not remove the due dates. I want to clear it off completely.

1 answer

1 accepted

3 votes
Answer accepted
Tuncay Senturk _Snapbytes_
Community Champion
July 20, 2018

Hello @Sridhar Gandla

Bulk update selecting (enable the checkbox near) "Due Date" option, with EMPTY field should clear the field.

change-due.png

Sridhar Gandla
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 23, 2018

Thanks.   I tired "EMPTY" and did not work for me as I tired EMPTY, NULL.  Did it worked for you?  I tired to even given all SPACES as well but no luck et all.

 

Please suggest  

Tuncay Senturk _Snapbytes_
Community Champion
July 23, 2018

Yes, I tried leaving the field empty as in the screenshot and it cleared the field.

Like Sridhar Gandla likes this
Sridhar Gandla
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 23, 2018

Super. Let me try in office tomorrow morning ! thanks for your prompt response/  I tied to write EMPTY Key word instead or EMPTY the field.

Sridhar Gandla
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 24, 2018

It worked .. Thanks you !!! 

Tuncay Senturk _Snapbytes_
Community Champion
July 25, 2018

Glad to hear that.

btw, could you please accept the answer so that other users would see it without diving into comments.

Simon Herbert
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 13, 2023

I can't get this to work ... Using the bulk change facility, selecting start date and end date and backspace deleting through the field / box, to get it to register that you want to clear the date results in initially nulling the date and then immediately setting it to today's date - despite what's indicated at the 'confirm' step.