How to cofigure "Original Estimate" and "Remaining Estimate"

srinivasan radhakrishnan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 9, 2013

Hi,

I need to add the "Original Estimate" and "Remaining Estimate" fields in newly created issue screen.

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 9, 2013

Add "Time Tracking".

The estimate fields are not really separate fields, they are derived from the time tracking data and worklogs, and the to get them used on a screen, you need time-tracking there..