I have a Scrum board where swimlanes are organised by stories. Stories without subtasks will show up as a single card, while the ones with subtasks are represented as swimlanes, which is great.
What I would like to achieve is to show a story as a single card when it's closed, no matter if it has or has no subtasks. We use quite a few subtasks, and it would make our board much cleaner if closed items were represented as single cards.
If all the subtasks are closed, but the story is not, I still want to show it as a swimlane.
Is this even possible?
Thanks,
Tamas
Hi Tamas
Not sure if Jira had a switch to exactly meet your requirement. But I do see a workaround: Add a quick filter into your board to hide the Done sub-tasks, and display only Story and incomplete sub-tasks.