Hi there!
At my company, we use other task status to cassify our activities as done (instead of actually "done" of Jira).
So, I just wanna know if is there a way to configure the burndown chart of Jira to be able to acept that - to classify activities as fineshed in that chart by the status we use here.
Someone know if is there a way?
Thanks! :D
Hello @Isabele Romanini Carvasan
This issue has been previously discussed and solved in this thread: https://community.atlassian.com/t5/Jira-questions/Burndown-on-custom-status/qaq-p/303998
😄
Thanks for your help!
I tried to do one thing mencioned in the thread you gave me: I removed the "done" column to Jira understand that my previous status was the "correct" instead of done.
Sadly, that didn't work :(
Do you know any method more eficient?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Within that thread, I think a good solution for you to try out is the implementation of the post function on transition to your 'Done' state: https://community.atlassian.com/t5/Jira-questions/Burndown-on-custom-status/qaq-p/303998#M249450
Should be efficient :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.