In my new generation JIRA project I would like to convert some of the predefined Story tickets into children tickets (sub-task) so that I can add them to another "parent" ticket.
Is there a way to do that ?
Hi Warren.
Thanks a lot for your reply that fully answers to my request.
Note: In french, it is named "Projet logiciel nouvelle génération" (New generation software project).
Regards.
I assume you mean Next Gen project, not New Gen.
If you open the story, click on the 3 dots in the top right corner, then click on Move.
You are than able to change either the Project or Issue Type. Click the dropdown for the Issue Type and choose Subtask, then a box opens to choose which parent to move it under.