How to convert time tracking logged in time automatically converted to story point in jira on-prem?
Generally, you don't. Story points are not equivalent to time.
Hello @khushboo_puri
Please provide more information about your use case.
Why are you trying to do this conversion?
Do you have a formula for performing that calculation?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Users in our jira do this manually.6hr = 1 story point.So we are looking for solution where story points are automatically updated based on time logged in jira on-prem.