We have a ticket that somehow had an Original Estimate given to it of over 2000h - I suspect it was a typo and was meant to be 2hrs or something. It was a ticket that had been created a while ago but we hadn't noticed the estimate discrepancy until recently when we were working on it.
We adjusted the Original Estimate to a sensible number but when we completed a Sprint we noticed that our charts like Burndown charts etc had become massively skewed because of the huge number that was originally there - and in the list of tickets at the bottom it still shows with the original high number.
The ticket is still in progress so has carried over the the next Sprint but in the reporting it is still using the initial value entered?
Is there any way to correct this?
Since there is no option to delete history entry, it effects the chart visual.
Also, there is an open ticket related to it. Please watch and vote: JRASERVER-69002
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.