Hello there,
Bescause JIRA limitations, we would like to be able to have an Automation function to copy Log Work to the parent Epic.
Could you kindly show us the steps for it?
Many thanks in advance!
Best regards,
Hi @Jorge ,
Please look at this example in the template library for how to sum up the sub-task original estimates.
https://www.atlassian.com/software/jira/automation-template-library/rules#/rule/1371692
You can use related issues to update the Parent issue. Next, you can use Automation action - smart values for the worklog values.
I hope that this helps!