Hi team,
I have multiple boards in a single project, now I want to restrict only one particular board to just create sprint /start sprint but they can view the board for checking the backlogs only.
Example scenario:
project: A --->03 boards --- visible to GROUP A, and Administrators
Board X, Board Y, and Board Z
HI,
Since the boards are showing the same issues or at least issues beloning to the same project, the boards follow the permissions on that project. The Manage sprint permission is a project permission and can not be set board by board.
You can however grant this permission to a group, but then they wont be able to start / stop sprints on all the boards of that project. You can do this by granting / ungranting the Manage sprints on the project.
Best practice here is to use project roles, then assigning the roles to permissions in the permission schemes.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.