When I view the Sprint Health. The color coded bar shows "Todo", "In-Progress", and "Done". The JQL pulls the blocked and in-progress status as part of the "In-Progress" total points however, I would like to include the points for "ready for deployment" status. This is a workflow step prior to "done" resolution.
Alternatively, I could also just show point counts for every status (not lumped together) on the color bar. Which ever is easier to paint the complete sprint picture. If someone can outline steps/edits for this.
Hello @Mary Padilla
Welcome to the Atlassian Community!
Per your description, I understand that you have an extra status in your Sprint called "Blocked" and the Story points in that status is added with the same color that the "In Progress" status in your Sprint Health Gadget. Is that correct?
In fact, the colors in the Sprint Health Gadget do not represent the issue statuses, but yes the Issue Status categories:
That being said, we understand the option to switch the Sprint health gadget to be based on the issue status itself would be a good feature in some cases, so we created the following suggestion to be considered by our PMs:
Configure the Sprint Health Gadget colors based on the issue status
Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.
As a workaround, you can use a report from a third-party app to display the sum of Story points of your issues separated by statuses. Here are some options:
Feel free to check any other options in our Atlassian Marketplace.
Let us know if you have any questions.
Yes, I noticed that certain status liked blocked are reflected in my "in Progress" on the bar. Which is fine, I'm looking to also add the ready for deployment status to the "in progress" on the bar as well. What controls this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Mary Padilla
Thank you for the explanation. Can you please confirm if you are using a Next-gen or Classic project?
Supposing you are using a Classic project, you must map the status "ready for deployment" to any column between the first and the last column of your board, also keeping it with no resolution set (Unresolved). Doing that, the status will be included in the "In progress" (yellow color) in the gadget.
These would be the detailed steps:
Let us know if you have any questions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.