I like to know the steps to export EPIC with all the stories under it to another Jira board . Please advise.
Hello @Anil vemula and welcome to the Community! You don't need to export ~ simply run a query (like the one below) and Bulk Change > Move, to your new project. This assumes that when you refer to another Jira board, you're referring to another project. If that's not the case, can you elaborate?
key = ABC-123 or "Epic Link" = ABC-123
Thanks Sciutti. Will this copy all the stories and sub-tasks under the EPIC to the new project?