Hello Community,
Team is working in working hours and not story points. Is there a report to show planned vs actuals in hours as measure unit? Team is working in sprints. Thanks!
Regards,
Jovanka
Hi @Jovanka Jovicic,
Try also the Team Velocity gadget offered by our Great Gadgets app. It can calculate by time estimates and can consider the subtasks in the calculation.
Optionally, it can display a Data tab with a nice report that you can export in CSV. This is an example.
This app offers other gadgets that supports time estimates, like Sprint Burndown Chart or Release Burndown Chart, which will make the project tracking much easier and efficient.
Take a look over this article from our blog, to make a better idea: Tracking an agile project that uses time estimates with Great Gadgets for Jira
I hope this helps.
Danut
Hello @Jovanka Jovicic
The Velocity Chart should show time instead of story points if the Estimation Statistic in your board configuration is set to Original Estimate.
Are you working with Jira Cloud or Jira Server/DC?
If Jira Cloud, are you working with a Team Managed project or a Company Managed project?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello, it will be company managed project. For now we are waiting for the jira access and will try to setup as suggested. Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.