How to hide card that have been DONE for while

Jake S
Contributor
August 22, 2023

I would like to hide cards from a Kanban board that have been set to DONE for a while, how can I do this?

 

I have tried writing some jquery like this but it didnt work : status != Closed AND status changed before -30d

I would think there may be a standard feature to do this.

1 answer

1 accepted

2 votes
Answer accepted
Dave Mathijs
Community Champion
August 22, 2023

Hi @Jake S 

In the Board Settings, under General, scroll all the way down. There you'll find:

Hide completed issues older than:

  • 1 week
  • 2 weeks
  • 4 weeks
  • Never mind, show all