How to move the kanban board to another project without losinh the tasks? Here the trouble that two projects are differ by the status of tasks(workflow)
Hi @Aizhan Kuanyshova ,
welcome to the community!
Board is something that can be configured for one or more project. Board structure can be shared through projects but tasks are project specific.
If you need to move tasks from one to another project you should perform a move or bulk move first so that your task will change project container.