Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to move tickets from one status to closed upon completing sprint

Scott Stephens April 19, 2017

We have a status called "Ready for PROD Deployment" .  This status is considerd in the DONE column from Agile board. 

I have a request to trigger teh status to move from Current status to "Closed" when we are making the sprint completed.

Is there a way to do this via some workflow operations to triger this?

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 19, 2017

You could code for this, but it's not a good idea.

Your developers and users are being lazy and, if I were being grumpy about it, ignorant.   Issues should be moved to the "done" column when the people dealing with them genuinely think they have been done.  "Meh, close sprint and just throw everything in the sprint to closed" just says that they don't care whether it's done, they're only interested in pretending that they're performing.

Closing a sprint should never just close everything in it.  Because no-one has really signed up to say "yes, it's done"

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events