Hi
I am trying to figure out how to implement this rule in Jira cloud. I would like notify the reporter when all the subtasks inside an issue have changed status to done. I have 3-4 subtasks in an issue and I set a rule that only when the subtasks are in status done, the reporter can transition the issue. But I also want to automate the notification when the subtasks are completed so that the reporter can transition the issue . Thanks,
Aditya
Hello @Aditya Aryasomayajula
Thank you for reaching out.
Per your description, I understand you would like to notify the reporter of an issue when all the related sub-tasks are done. Is that correct?
I believe the following automation rule should work for you:
This would be the background of the rule:
Let us know if you have any questions.
Hi Peter,
Thanks a lot for reaching out. This is exactly what I am looking for. I was not aware how powerful the automation tool in jira is. I just have one question...does this rule ensures that the email is sent to the reporter only when all the sub-tasks are completed and not when one sub-task is done? Can you confirm that please. Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You are welcome @Aditya Aryasomayajula
Indeed, Jira automation is a very complete tool.
With the rule I provided above, I can absolutely confirm that the notification will only trigger when all the sub-tasks of the parent are done. You just need to make sure you selected the condition "All match specified JQL" in the Related issues condition:
Let us know if you have any other questions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
A followup to this question - Is it possible to add to the sent email a list of all of the finished subtasks ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yarden, I was able to accomplish this by the following text in bold within the body of the email. Hope this helps.
Hello {{Issue.Lead Developer.DisplayName}},
All of the subtasks on {{Issue.key}} are Status = Done and are ready to be deployed to QA.
Please coordinate with the Lead Developers of Subtasks and deploy to QA.
https://nationaleducationassociation.atlassian.net/browse/{{issue.key}}
Labels: {{issue.labels}}
Related Subtasks: {{issue.subtasks}}
--
What I received in the actual email was:
All of the subtasks on NEA-3795 are Status = Done and are ready to be deployed to QA.
Please coordinate with the Lead Developers of Subtasks and deploy to QA.
Labels: Mulesoft, Salesforce
Subtasks Lead Developesr: Sharon Youmans
Related Subtasks: NEA-4704, NEA-4705
Thank you,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.