Hello Team,
Our issue type hierarchy is defined like below, this defined in cloud using advanced roadmap.
initiative--> Epic--> Story
story is linked to epic using 'Epic Link' and epic is linked to initiative using 'Parent Link'
I want to update the epic status to done once all the linked stories are done and when all epics are done then linked parent initiative should moved to done.
How do we achieve this is cloud?
Does automation rules support this in cloud?
Thanks
Pratibha
Hi Pratibha,
Yes, you can use this in Cloud. I would go ahead and change your rule to use the Parent field in both cases instead of using Epic Link and Parent Link.
Here is an example that works for me. Just change out the condition as needed.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.