How to set the automation for sub task/ task’s change issue status refer to epic issue status?

Aco QA
Contributor
November 3, 2020

Please help to provide the step by step setting guideline to me?

1 answer

0 votes
Guilhem Dupuy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 3, 2020

Hello,

I'm not sure I fully understood your need but you can use the following process in order to change an epic status to "Done" if all of it's stories or tasks are "Done" too. This method can be adapted to complete a task when all of its subtasks are done too.

  1. When : issue transitioned
  2. If : issueType = Story
  3. Rules for linked branch : for linked Epic
  4. If all stories status is : "Done"
  5. Move current issue status to : Done

Suggest an answer