How to track work my members outside the main team?

Pete Reiter
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 21, 2021

I have a project that needs some work done from a few key individuals outside of the main team. These will be specific stories assigned to specific people.

I want to track these issues, but if I add the issues to my backlog and add the people to my team that will make it difficult to track velocity.

What is the best practice for tracking these issues?

1 answer

0 votes
Suvarna Gaikwad
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 21, 2021

@Pete Reiter Components can be used to segregate and track these issues in two stages like below.

Stage 1 to track other team's issue.

  1. Create a component in your project say ProjectX. For example, TeamB. Give relevant name as per your requirement.
  2. Assign component created in step 1 to issues that are being handled by other team.
  3. Create a filter as mentioned below to track such issues. project = ProjectX and component = TeamB
  4. You may want to use filter created in step 3 in Dashboard to track such issues in graphical view.

Stage 2 to remove above issues from Backlog:

  1. Create another filter as mentioned below to exclude other team's issue. project = ProjectX and component != TeamB
  2. Use filter created in step 1 in agile board which is being used for project. It will prevent those issues from appearing in backlog.