Hi,
I need help! A few things are going drastically wrong with JIRA for us. One is that things that were in the done column somehow did not get captured and they are not counted in the velocity and all the charts are thrown off because it somehow did not capture the stories that were complete. Is there any way to go back and try to troubleshoot? Once the sprint is closed, I don't see a way to go back. Help! It's happened two sprints in a row now and I can't figure it out!
Any way to get someone on the phone to walk me through fixing this?
I could not have visibility into the charts once the sprint is closed. There's no way to go back and correct any issues that would help me correct the charts?
Hi Ming!
Currently is not possible to reopen a sprint in JIRA, we have a feature request for it in https://jira.atlassian.com/browse/GHS-7804, but no plans to implement in the near future, sorry.
My advise would be to you to create a test project in your instance to troubleshooting the close sprint process.
Cheers!
Teilor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.