I have created my first jira project.
Q: How to make an existing task a sub task to a newly created task?
Thanks Scott
You can convert multiple tasks into subtasks via bulk issues
For doing so, perform a search > bulk change > Move Issues.
Move into the same issue and change the issue type to sub-task.
It will also ask you the parent issue that it will be linked.