Our team works on multiple projects at a time. How can we select all those high priority items from multiple projects and work on them in one sprint?
I created JIRA Rapidboard. It is showing me all the items inside the indisividual projects in the current sprint.
Is there a way I can actually have multiple backlogs for each project but have one active sprint?
You can create a board and define for this board a filter (board settings -> general), which would select all issues with high priority. Then you could manage these issues in one sprint.
A board is a view of issues, which are selected from the projects by the filter. So yes, you can have many projects on one board, and create a sprint from the backlog you get there.
Then you can create other boards with different filters and their own backlogs.