I want the Completed Work line to be based on released issues in the Burnup Chart What should I do?

delaram nezami
Contributor
November 26, 2023

I want the Completed Work line to be based on released issues in the Burnup Chart
What should I do?

2 answers

0 votes
Danut M _StonikByte_
Atlassian Partner
November 26, 2023

Hi @delaram nezami,

Try the burnup charts offered by our Great Gadgets app. They are highly configurable and do not use the resolution field but the issue status. 

image.png

image.png

If you need any help, please contact support@stonikbyte.com

Thank you,

Danut Manda

0 votes
Ste Wright
Community Champion
November 26, 2023

Hi @delaram nezami 

It's not possible to modify how the Burnup Chart works at this time.

You could...

  • Ensure issues are only transitioned to "Done" (or, the right-hand column) once released.
  • Add an additional Status to capture issues with are built but not released, so the last status/column is for released issues.
  • Limit the transition to Done unless the linked version is released.

...to help ensure the Burnup shows what you require.

---

Alternatively, you could get an App which might give you greater flexibility in setting up your needed reporting.

Check out Apps such as...