If I lose date when change a screen schemes?

Paulina Mijal September 16, 2021

I want to change a screen schemes in Jira Project. The schemes are diffrent - some of their fields are different. When I change it, if it is possible that for example the description that was previously written will disappear and will not be moved?
Thank you in advance.

Best Regards, 
Paulina Mijal

 

1 answer

1 accepted

2 votes
Answer accepted
Pramodh M
Community Champion
September 16, 2021

Hi @Paulina Mijal 

The Data is stored in Custom field and not the screen or screen schemes, you can change Screen schemes and it will not affect in any way on data you have stored.