I have created a sprint 1..Estimated 5 hrs..and burnt 3 hrs...
Then i am pushing the same story to next sprint...Can my Time tracking field can start from "Zero"...
Asking this because..Time tracking's estimates....is prelogged when i push to next sprint too..
Need your help on this
Hello Deepan,
Thank you for reaching out.
It is the expected behavior to keep the Time tracking field of the issue even after the current Sprint is closed.
Currently, you are able to manually delete work logs and set the Original/Remaining Estimate to 0h, however, there is no way to bulk delete work logs.
In fact, we think that the bulk edit of Time Tracking would be useful functionality, so we created a feature request to get it implemented:
- Bulk Edit: Time Tracking Estimates
Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.
As a workaround, you can bulk edit issues using the JIRA REST API.
Let me know if you have any questions.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.