Hi,
Status has been changed from move to production (sprint 4 got completed) to development complete. (started new sprint)
In sprint report status column for issues till sprint 4 is still showing move to production but in that particular issue detail view its showing development complete.
so i just removed the status that is mapped in board.
so now in reports its displaying issues removed from the sprint.
so i want all the issues to be displayed in the sprint report.
Please provide me a solution asap.
Regards,
Abhishree Nagesh.