We have scrum boards that include more than one project and have 2 issues.
- The board does not link to the projects
- The projects in which sprints are created seems random
How do we resolve these issues?
Hey Brian,
A board can only have location (linked project). You could copy the board to you other project (should just be a one time thing and then they would keep in sync) or you could create a project to house all of your multi-project boards (if it's a common issue you run into).
For Sprints, if a Sprint wasn't created on a specific board, unless there is an issue assigned to that Sprint it won't show up on the board (hope that makes sense).
Tyler
Thank you Tyler
I see sprints created from all over the system in my board if i include relevant tickets
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.