In our Jira sprint, we have added "Resolved" and "Reopened" statuses in addition to the default statuses of "To Do," "In Progress," and "Done." However, we have noticed that whenever a ticket is in the "Resolved" or "Reopened" status, it is included in the "In Progress" total original estimation on the top right bar.
Is there a way to include the original estimations of all statuses, including "Resolved" and "Reopened," in the total original estimation displayed in the sprint view? We would like to have a more accurate representation of the total effort remaining in the sprint.
Any suggestions, workarounds, or pointers to relevant plugins or configuration changes would be greatly appreciated.
Thank you for your assistance!
Hi,
Looks like, the problem is with wrong Status Category.
In Jira, status categories are used to classify and group statuses based on their intended purpose or usage. The status category helps provide additional context and understanding about the status of an issue within a Jira project. There are three default status categories in Jira: "To Do," "In Progress," and "Done." Here's a breakdown of each status category:
As I see, you added Reopened status to category "In Progress". I suppose, you added Resolved to similar category. It's better to change categories for that statuses.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.