Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is it possible for the Parent Task dates to automatically update according to the child dates?

Kristine Gemici
Contributor
August 5, 2022

In Jira Software, the board settings can be changed so that the parent task will automatically populate once the child tasks are entered on the timeline... Does Jira Work Management also have this feature? If so, how can this be updated?

8-5-2022 4-57-56 PM.jpg

 

1 answer

1 accepted

3 votes
Answer accepted
Hana Kučerová
Community Champion
August 7, 2022

Hi @Kristine Gemici ,

I don't think this is implemented. But I believe you should be able to create automation rule to set the dates to the parent issue.

Kristine Gemici
Contributor
August 8, 2022

Thank you Hana! How can I set this rule?

Hana Kučerová
Community Champion
August 8, 2022

Please, see here. There's very rich documentation for automation feature.

Like Kristine Gemici likes this
Kristine Gemici
Contributor
August 8, 2022

Thank you!

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events