Hello,
I am wondering if there is a way to modify the settings for burndown charts in company-managed projects? I was wondering if there is a way to have the burndown chart consider a task to be done when it is in a column other than the "Done" column. For example, we currently have a "Regressed" column followed by the "Done" column. I would like to change the chart so once a task is moved to "Regressed" that in the burndown chart the task would be considered as done, and the chart would go down. Currently I can not do this and the burndown chart will only update once the task is moved to the last column, which is "Done"
Thanks for any help anyone can provide!
Welcome to the Atlassian Community!
No, you can't change the column for "done". But you can put the "regressed" status in the last column to make it count as done.