Ritesh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 5, 2019

I am working on project which include two difffrent teams but we have single project .

The single burndown chart is created to determine the velocity of overall project and team. Is it possible to create two diffrent burndown charts based on team A or team B . Currently  we are using the component to diffrenciate diffrent teams ?

1 answer

1 accepted

0 votes
Answer accepted
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 5, 2019

Hi @Ritesh 

So if you create 2 boards, using the filter from the project, but for one board you add 

component=TeamA to the filter and for the other you add component=TeamB.

Each board would then show the burndown for just that team's tickets, and the project would have the overall burndown.