Hello Team...I am looking to convert several tasks into subtask in Jira....I tried to do a bulk change but subtask is not an option...please advise...thank you
For bulk changes they have to be converted to like tasks. However if you click the more button you should have a convert option in each issue. Another option is to make an Epic and make the corresponding tasks part of that Epic, which maybe less work but accomplishes something similar.