So I have loaded the gadget for Sprint burndown in story points to my Dashboard. However, since most of my user stories do not close until after day 6 of my 2 week sprint, (Agile) it really does not properly represent Sprint progress. What I am looking for is a report that starts with total task hours for the sprint and daily burndown. Is this possible with Jira?
You have to go into your board settings and then under "Estimation" there is an option to select "Original Time Estimate" instead of "Story Points"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Actually, you can do the estimation in Story Points but do the burn down using time entered. You just need to select "Remaining estimate and time spent" under TIme Tracking.
See https://confluence.atlassian.com/jirasoftwarecloud/configuring-estimation-and-tracking-764478030.html#Configuringestimationandtracking-Settingestimationstatisticandtimetracking for more details.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If your board is setup to use Story Points for Estimation then that is what you get. If you want hours you need to select a different estimation method, e.g. Original Time Estimate. Of course this moves you away from Story Point estimation so make sure that is what you want to do. Example image....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.