Is there a way to compare Tempo time to Original Estimate from JIRA?

Audra Bell December 14, 2023

Is it possible to link the Original Estimate field from JIRA to the actual time tracked in Tempo?  Can these be displayed on a report in Tempo?  We would like to compare our original estimates with the actual time tracked in Tempo.

1 answer

1 vote
Ivan Lima
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 15, 2023

It's possible to get a report with the original estimate, time spent, etc. What type of comparison are you looking at? Visually, yes, a report should do it; you can also use the work ratio for calculations or automation if that's the case.