Is there a way to restrict time logging on cards in a past sprint?

Cass
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 22, 2019

We have several cards that are marked 'Done' that users are accidentally tracking time on. Is there a way to restrict users from being able to log/track time on tickets in a past sprint?

1 answer

0 votes
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 25, 2019

Hi Cassandra,

You could do this with the Workflow Property "jira.permission.work = false" set on the 'Done' Status

Check out the following guide from j-tricks which has a really good breakdown of the functionality, that goes a bit deeper into the functionality:

Regards,
Earl