Is there a way to see total estimated points on a future sprint?
We use JIRA 7.12 server version.
Yes it is possible, but you will need to purchase a license for the JIRA add-on Adaptavist Scriptrunner. Then you can do a JQL like the following:
project = <project name> AND sprint in futureSprints() AND issueFunction in aggregateExpression("Total points", "storyPoints.sum()")
This sums up all of the Story Points for issues assigned to future sprints.
You can also change 'futureSprints()' to a specific sprint number (e.g. '421'.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.