Alright here is my scenario, I have a release planned ( Version 1.0 ) with multiple cross project teams working on it. And these teams involved, have their own sprints running in parallel where they take stories from multiple releases.
Now what i want to see is the progress of my release ( Version 1.0 ) as the sprints progress. Is it possible?
If not, can someone please recommend an alternative to view a release burndown?
Yes. You can track the whole release in a single release burndown chart by using the Release Burnup Burndown Chart gadget offered by our app Great Gadgets for Jira.
This gadget is based on a filter. So all you have to do is to create a filter that includes all the issues from your release. Then configure the gadget to use the new filter, set the release start/end dates and the estimation. It supports various estimation methods. Optionally, you can choose to display forecast, milestones and include the sub-tasks in the calculation.
See also this blog article: Cross-teams release burndown chart in Jira with Great Gadgets app
If you have any questions, please contact us at support@stonikbyte.com
Danut.