Is there any possibility to visualise in backlog if issues were added after sprint start date

Aravind Koushik Gobburu
Contributor
August 31, 2021
Is there any possibility to visualize in the BackLog View if the issue was added after sprint start date or not? If so how can we do this.

1 answer

1 vote
Jack Brickey
Community Champion
August 31, 2021

Here’s an idea that you could consider and research the implementation.

If you have a scripting function or an automation addon such as automation for Jira then you could create a custom field and set that field true using automation if the issue is added after the sprint start. Then you could add that field to the backlog card display.