Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is there any way to add more statuses to 'Done' StatusCategory in Next-Gen project?

David Peles January 4, 2021

Hi All, 

It seems that even a secretin status (Rejected)is set with 'Done' StatusCategory (Green color) on the workflow. when I complete a sprint I still see the items as 'UnDone' and I am required to move the items back to the Backlog \ move to next sprint.

Any directions \ workarounds so I can fix it Reject.JPGbl.JPG

Anyone can assist ?

 

2 answers

1 vote
KAGITHALA BABU ANVESH
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 4, 2021

Hi @David Peles ,

Please go to board 

1. let's check does the "Reject" status is placed under "Done" column.

2. any resolution is chosen while "Reject" jira Task.

 

If above both are placed correctly , then there is no issue.

  

0 votes
John Funk
Community Champion
January 4, 2021

Hi David,

Make sure the Reject Status is in the last column. Only statuses in the last column on a Sprint board will be considered "Done" and not moved. 

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events