Hi All,
It seems that even a secretin status (Rejected)is set with 'Done' StatusCategory (Green color) on the workflow. when I complete a sprint I still see the items as 'UnDone' and I am required to move the items back to the Backlog \ move to next sprint.
Any directions \ workarounds so I can fix it
Anyone can assist ?
Hi @David Peles ,
Please go to board
1. let's check does the "Reject" status is placed under "Done" column.
2. any resolution is chosen while "Reject" jira Task.
If above both are placed correctly , then there is no issue.
Hi David,
Make sure the Reject Status is in the last column. Only statuses in the last column on a Sprint board will be considered "Done" and not moved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.