Issues completed outside of sprint not showing in the burndown chart

Iva Kvakic
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 16, 2020

Hi, 

We are in an active sprint, and the burndown chart works great, except for the bottom part "Issues completed outside of sprint", where it is not showing anything, although we have completed issues outside of sprint. Why is this not showing up?

 

Thanks!

1 answer

0 votes
Lenin Raj
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 16, 2020

Hi @Iva Kvakic 

I could think of a couple of things:

1. Were those issues marked as Done or resolved as per your workflow?

2. Was it resolved "before" the sprint was closed?

Iva Kvakic
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 16, 2020

Hi @Lenin Raj 

1. Yes, they were marked as Done.

2. Yes, they were resolved "before" the sprint was closed and after it was started, i.e. during the currently active sprint. 

 

The only thing that I can think of is that the stories that were marked as Done during the sprint were also created after the sprint was started. However if this is the case it makes no sense in terms of the feature usefulness. Issues resolved outside the sprint should appear in any case in order for us to be able to determine future velocity appropriately.