Issues do not appear as "DONE" at SPRINT completion

matheus nascimento camargo July 25, 2018

When closing the sprint, it informs that there is no one in done.
The screen below, where, when executing the "Complete Sprint" button, it shows the message that "0 issues were Done" exists.

erro1.jpgerro2.jpg

2 answers

1 accepted

2 votes
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 25, 2018

In a scrum board, an issue is considered DONE only after it reaches the right most column. Not when a resolution is added to the issue or when it reaches a status named "Done".

In this case, you have to map "Done" status to the last column on the board.

matheus nascimento camargo July 25, 2018

I needed to put all the stories in the last created status. In this case, it was not "done." It was "Released".
Thank you for your help,

0 votes
Moses Thomas
Community Champion
July 25, 2018

@matheus nascimento camargoI see 0 days  remaining  to  complete sprint,  so  most likely you  did not  close any  issue before you  time elapsed.

 

Best!

matheus nascimento camargo July 25, 2018

erro1jpg.jpg

matheus nascimento camargo July 25, 2018

Hi, thanks for your reply, but I finished in that elapsed time.

Suggest an answer

Log in or Sign up to answer