Hello All,
We have two sprints in our project Sprint 1(Active Sprint) and Sprint 2(Future Sprint).
We have 4 workflow statuses To Do, In Progress, Done, Accepted.
When status moves to To Do, In Progress, Done and Accepted we are able to see issues in Sprint 1.
When status moves to To Do, In Progress, Done we are able to see issues in Sprint 2 but when the status of an issue moves to Accepted state issue are not showing up in the Sprint 2.
Do I Miss anything on the board configuration?
Thanks,
Manikanta.
Dear Manikanta, hi!
Often issues dissappear when it get a resolution.
In Jira resolutions mean that issue is closed.
Check if issue get resoution.
Best regards,
Vasiliy
Hi @Vasiliy Zverev,
Thanks for the reply!
Issue resolved after adding "Accepted" column on Active sprint board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So, I think this is the reason.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.