Good morning :)
I created a Sprint Board and insert a new zone "Zone" (you can see it in the screenshot). In this zone I want to park tasks that are allready done but I know that some how in the future the issues of the tasks will maybe change. I don't want to mark the task as "done" or "in progess". Do I have configure my Jira administration? Can you help me to solve this problem?
Cheers
Hello Maximilian,
Thank you for reaching out to Atlassian Community!
On next-gen project, currently, there are only three types of statuses: To Do, In Progress and Done.
It's not possible to configure the type of status of each column. The first one will be To Do and the last one Done and the statuses between those two will be In Progress.
If you need to configure the status of the tasks to a different one, I'd suggest you use a Classic Software project where the option is available:
If you have any other questions regarding this matter, please let us know.
Regards,
Angélica
Thank you very much. Your answer was useful for me!
Regards,
Max